Poland opens door to CfD support for private small nuclear reactors
Poland sees the state price guarantee backing its first nuclear plant as the basic support for small modular reactors too, a deputy energy minister said, wnp.pl reported on November 17.
"In Europe, because of very complicated conditions, developing nuclear power without state support is practically impossible. The CfD [contract for difference] model is the basic support mechanism for nuclear power, both large and small-scale," Deputy Energy Minister Wojciech Wrochna told a workshop in Warsaw on the BWRX-300 small modular reactor (SMR), organised by GE Vernova, SGE and the Atlantic Council. "The government is ready to start talks with investors and with the European Commission to work out the right framework for this support," he added.
Until now the contract for difference has been tied to the state-owned Polskie Elektrownie Jadrowe (PEJ) and its large plant at Choczewo on the Baltic coast, where the European Commission approved a 40-year two-way contract in December 2025. Putting SMRs under the same mechanism points to how Orlen Synthos Green Energy (OSGE), part-owned by a private investor, could finance its planned fleet, and depending on the contract design, consumers and the state could carry part of the risk. OSGE applied to the energy ministry in June for a contract for difference covering 14 BWRX-300 units, and there is little sign the talks will end soon, wnp.pl reported.
OSGE is a joint venture of state-controlled oil and power group Orlen and Synthos, the chemicals group owned by billionaire Michal Solowow, and plans its 14 reactors at Wloclawek, Oswiecim and Stalowa Wola. The partnership has been strained: in August the government said it would bring in the state-run Polish Development Fund to break a deadlock between the two 50% owners, and in October Orlen and SGE agreed a phased approach to the first unit at Wloclawek, with a support model to be worked out with the energy ministry among the next steps.
Wrochna, who is also the government's plenipotentiary for strategic energy infrastructure, knows both sides of the programme. He was previously a vice-president of OSGE and an adviser to PGE EJ1, the company now called PEJ, and he co-leads Poland's team negotiating the engineering, procurement and construction contract for Choczewo with the Westinghouse-Bechtel consortium.
He told the workshop that the potential of SMRs "may be even greater than that of large-scale projects". Poland is seen as a leader of the "nuclear renaissance", he said. "It is a paradox, because in reality in Poland we currently operate only a research reactor," he said, referring to the Maria reactor at Swierk near Warsaw.
PEJ plans three Westinghouse AP1000 reactors at Choczewo, a project the Commission put at around €42bn, and has just signed a letter of intent with Westinghouse-Bechtel on long-lead components. SGE is taking the BWRX-300 abroad, most recently in a deal with Bulgaria's NEK and Blue Bird Energy.