Cambodia lists record $99mn bond for 350 MW solar farm
Cambodia listed its largest bond to date on November 16, a $99mn green issue by SchneiTec Jupiter to support a 350 MW solar farm in Pursat province.
The bond anchors a $150mn financing package, according to a statement from the Global Green Growth Institute (GGGI), which supported the issue. The farm in Krakor district is one part of the 930 MW Chheu Tom solar complex, the largest solar power development in Southeast Asia, and is expected to power more than 200,000 Cambodian households. Yuanta Securities (Cambodia) was the sole financial adviser on the package, which combines six bond tranches with a loan, Cambodia Investment Review reported.
Cambodia's first project bond came only in April 2025, when sister company SchneiTec Dynamic sold a 15-year, KHR196.64bn ($48.2mn) green issue to build a 60 MW plant in Kampong Chhnang. Doubling the size within 19 months suggests the country's small capital market can now carry long-term infrastructure money, but so far one business group has used the route.
Australia's Cambodia Australia Partnership for Resilient Economic Development (CAPRED) gave technical help to the Securities and Exchange Regulator of Cambodia (SERC) as it drafted a July 2025 regulation on infrastructure debt securities, which lets public and private companies raise long-term finance for eligible projects.
The draft rules were approved in May 2025. Australia also pays part of the issuance costs for early movers such as SchneiTec, while Luxembourg funds the Cambodia Sustainable Bond Accelerator, run with GGGI technical assistance, according to the state news agency AKP.
“We encourage more businesses and investors to follow, taking advantage of these financial instruments,” said Derek Yip, Australia's ambassador to Cambodia.
The Council for the Development of Cambodia approved five renewable projects worth more than $1bn in the first half of 2026, among them a $226mn, 350 MW solar plant in Pursat, two 150 MW wind farms in Mondulkiri and a $300mn, 200 MW solar scheme in Stung Treng. The Pursat plant matches the new bond's project in size and province, though the council's statement did not name the developer.
Bank lending still does most of the work. Another group company, SchneiTec Legacy, signed a $182mn syndicated loan this month for 1,000 MWh of battery storage in Kampong Chhnang and Pursat. The 28 companies listed on the Cambodia Securities Exchange had raised about $720mn in total by September 10, 16 of them through corporate bonds.
Solar demand is growing faster than planners expected. Cambodia has nearly 1.5 GW of installed solar capacity, already past the 1 GW and 1.3 GW its power development master plan set for 2030 and 2035, and solar supplies more than 10% of national generation, according to a briefing note from the Institute for Energy Economics and Financial Analysis (IEEFA) in June.
The next large issue will show whether the rules work for anyone else. If it comes from a borrower other than SchneiTec, Cambodia will have a project bond market rather than a run of one group's milestones.