Pakistan plans renewables for 93% of new power capacity
By 2035, Pakistan aims to bring 15,206 MW of renewable generation online, including hydropower, which would account for about 93% of the new capacity planned for the coming ten years, according to a November 18 report in The Nation. Official documents reviewed by Wealth Pakistan show that Pakistan's National Electric Power Regulatory Authority (NEPRA) has given its approval to the Integrated System Plan (ISP) 2025-35, a blueprint envisaging 16,406 MW of additional generation overall.
The plan would lift Pakistan's installed capacity to about 62,383 MW by 2035, with renewables and hydropower making up over 60% of the total. The National Electricity Policy 2021 and the National Electricity Plan 2023-27 set a target of a 60% renewable share by 2030. Utility-scale renewables, counting hydropower, now represent about 35% of installed capacity. That figure rises above 45% once distributed solar connected through net-metering is added.
Nuclear generation accounts for the 1,200 MW not covered by renewable projects. Solar photovoltaic installations under net-metering form the largest block, at 8,120 MW, followed by hydropower at 4,505 MW and wind at 2,581 MW.
K-Electric will take on 1,391 MW of the wind capacity, while the remaining 1,190 MW goes to the grid operated by the National Grid Company/National Transmission and Despatch Company. Additions to capacity will be guided by Pakistan's Indicative Generation Capacity Expansion Plan (IGCEP), a framework grounded in least-cost planning of the system as well as current policy and procurement rules.
The ISP also examined whether battery energy storage systems (BESS) would be needed to keep the grid stable as more renewables come online. It identified an indicative need for 600 MW of battery inverter capacity backed by around 1,500 MWh of storage, at an estimated cost of $900mn to $910mn.
NEPRA declined to approve that spending and left battery storage out of its approved Revised Base/Recommended Case. The regulator instructed the Independent System and Market Operator to carry out a full technical and economic study before storage can be considered in later plans.
The National Grid Company has separately finalised a 20 MW/20 MWh pilot battery project at the Jhimpir-I grid station, now costed at $15.7mn.
The Asian Development Bank is linked to proposed storage schemes of 500 MW in the south under Phase-I and a further 500 MW in the north under Phase-II. The first phase, priced at around $400mn, is due to start commercial operation in the 2029-30 fiscal year.