US FERC approves Sabine Pass LNG Stage 5 expansion project
The US Federal Energy Regulatory Commission (FERC) has approved the construction of Cheniere Energy’s (NYSE: SPL) Sabine Pass Liquefaction (SPL) Stage 5 expansion project in Louisiana.
Sabine Pass was the first major liquefaction project to come online in the US and has been in production since 2016. It consists of six liquefaction trains, each with a capacity of 5mn tonnes per year (tpy) of LNG, for a total capacity of roughly 30mn tpy.
Cheniere intends to build the SPL Stage 5 expansion in two phases. Under the first phase, the company will add one more liquefaction train, with a capacity of around 6mn tpy, as well as a 1mn tpy boil-off gas (BOG) reliquefaction unit and compressor, tie-ins to existing infrastructure and other associated facilities.
Then, under Phase 2, Cheniere will add two further trains, Trains 8 and 9, which will also have a capacity of 6mn tpy each. Alongside further tie-ins to existing infrastructure it will also add a ground flare system, three new BOG compressors and other associated support infrastructure. Additionally, it will add capabilities to facilitate simultaneous LNG loading to two of the three berths at the terminal.
Cheniere has already entered into a lump-sum turnkey (LSTK) engineering, procurement and construction (EPC) contract with Bechtel for Phase 1 of the SPL expansion and has issued a limited notice to proceed (LNTP) with early engineering and procurement. The company said earlier this year that it was targeting an FID on Phase 1 of the expansion by early 2027, subject to various factors including receiving the necessary regulatory approvals. With the FERC authorisation granted, the company appears to be on course to achieve this.
Indeed, Cheniere’s chairman, president and CEO, Jack Fusco, said on the company’s third-quarter earnings call in late October that with FERC approval expected by the end of the year, Cheniere would reach FID “very quickly thereafter”.
The FERC has also authorised Cheniere to expand the Creole Trail pipeline and the Sabine Crossing pipeline in order to build and operate a new interstate gas pipeline serving Sabine Pass.
The SPL Stage 5 expansion is part of an ongoing series of capacity additions for Cheniere. In early September, the company announced that it had achieved the substantial completion of the Corpus Christi Liquefaction (CCL) Stage 3 project at its other LNG export terminal, Corpus Christi in Texas. The company is currently seeking regulatory approval for a further expansion stage at the Corpus Christi site.